EV Charging Design Standards for UK Commercial Sites

A commercial EV charging installation in the UK is designed around BS 7671 (the IET Wiring Regulations, including Section 722), the IET Code of Practice for EV charging equipment installation and the Electricity Safety, Quality and Continuity Regulations 2002. The equipment must also meet BS EN 61851 and, where it applies, the Smart Charge Points Regulations 2021. Public sites add consumer rules and accessibility guidance on top. This guide explains what each one means for the design of your site, in the order you will meet them.
TL;DR
Core electrical standards: BS 7671, the IET Code of Practice and ESQCR 2002 govern every commercial installation, and chargers must meet BS EN 61851.
Section 722 shapes the circuit: each charging point needs its own RCD protection, a plan for PME earthing outdoors and suitable ingress and impact protection.
Smart functionality is a legal design input: applicable non-public chargers need smart features, demand-side response and default off-peak settings.
Site type changes the rules: new non-residential buildings in England, public chargepoints and grant-funded projects each bring extra requirements.
Design for the supply first: a proper maximum demand assessment and load management decide how many chargers your site can run, and at what power.
Table of Contents
The standards that govern commercial EV charging design
Government guidance is clear on the baseline. Commercial chargepoint installations must follow BS 7671, the IET Code of Practice and ESQCR 2002, and the equipment must meet BS EN 61851 and the Smart Charge Points Regulations 2021. That specification was updated on 30 April 2025.
It helps to see these as layers rather than one rulebook.
Layer | What it covers | Why it matters to your design |
BS 7671 (IET Wiring Regulations) | Electrical installation safety, including Section 722 for EV charging | Sets protection, earthing and circuit requirements |
IET Code of Practice for EV Charging Equipment Installation | Practical installation guidance that supports BS 7671 | Covers supply assessment, load curtailment, testing |
ESQCR 2002 | Safety and continuity of electricity supply | Affects connection and earthing arrangements |
BS EN 61851 | Product standard for conductive charging systems | Your chargers must conform |
Smart Charge Points Regulations 2021 | Smart functionality for applicable chargers | Drives charger selection and software |
Public Charge Point Regulations 2023 | Pricing, payment, reliability for public chargers | Applies if the public can use your chargers |
The Competition and Markets Authority described the wider picture in its market study: product standards enforced by OPSS sit alongside consumer experience rules, while Ofgem oversees electricity supply. In practice that means your electrical contractor, your charger manufacturer and your charge point operator each carry part of the compliance picture. A good design pulls them together before anything is ordered.
How BS 7671 Section 722 applies to your chargers
Section 722 is the part of BS 7671 written specifically for electric vehicle charging installations. Three areas drive most design decisions.
RCD protection
Section 722 requires each charging point to have its own Type A or higher RCD rated at no more than 30mA. The section also requires measures against DC fault currents. These include Type B RCDs or devices that disconnect at 6mA DC. Many commercial chargers have DC fault detection built in, so the choice between external Type B protection and integrated detection is a charger selection question as much as an electrical one.
For a multi-bay site, this has a cost and space effect. One protective device per charging point means moreways in the distribution board, or a dedicated charger distribution board, so plan the enclosure early.
Earthing, including PME
Most UK supplies use protective multiple earthing (PME). It is a problem outdoors because a fault on the supply neutral can put dangerous voltage on a vehicle body. BS 7671 Section 722 prohibits PME for outdoor or potentially outdoor-facing charging points unless specific mitigation is used, such as an earth electrode or voltage-operated protection. The IET lists five methods in total.
On a car park this has real design consequences:
An earth electrode needs suitable ground and space, and its resistance must be tested.
Voltage-operated protection is built into many chargers, but it needs to be specified.
Bays under a canopy or inside a building may still be treated as potentially outdoor, so the designer needs to judge each layout.
Enclosure and impact protection
Equipment outdoors must be at least IPX4 and IP4X, and equipment in public areas and car parks must be protected against impact, with IK07 one option. Bollard or wall mounting, kerbs and wheel stops all form part of that protection, so the layout drawing matters as much as the charger datasheet.
Designing for supply capacity and load management
The biggest question on most commercial sites is not the charger. It is the supply. The IET Code of Practice says designs should assess supply adequacy and maximum demand, including DNO requirements, distribution switchgear sizing and final-circuit wiring, and account for load curtailment where it is used. The Code of Practice separates three things that are often confused: the maximum demand that the distribution network operator (DNO) sees, the rating of the distribution switchgear, and the wiring of each final circuit.
A practical sequence looks like this:
Survey the existing supply. Record the incoming capacity, the site’s measured peak demand and the condition of the main board.
Define the charging need. Count vehicles, dwell times and the daily energy each one needs. A fleet that parks overnight needs far less power per bay than a site that must turn vehicles round in an hour.
Apply diversity and load management. Dynamic load management shares available capacity between active chargers and the building, so you can install more bays than the raw supply would allow at full power.
Check with the DNO. If the design needs more capacity, or generation or storage is involved, the DNO application becomes the long-lead item.
Size the switchgear and final circuits to the managed maximum demand, with room to expand.
Our guide to EV charging power requirements for UK businesses goes deeper on kW, kVA and capacity. If budget is the driver, commercial EV charger installation costs shows where supply upgrades typically sit in a project.
Load management is also a design choice with a compliance dimension. If curtailment is part of your design, the Code of Practice expects it to be accounted for in the maximum demand calculation. It should be documented, not assumed.
Smart charging rules built into the design
The Electric Vehicles (Smart Charge Points) Regulations 2021 came into force on 30 June 2022. They require applicable non-public, non-rapid car and van chargepoints to have smart functionality, demand-side response capability and default off-peak charging hours.
For a workplace or depot, that tells you three things when you specify equipment:
Choose chargers that can receive and act on signals, and connect them to a back-office platform that supports this.
Expect default off-peak charging settings, which suit overnight fleet charging well.
Keep documentation showing that each unit meets the rules, because this is the kind of evidence a compliance check asks for.
We set out the practical steps in our three-stage guide to UK smart charging compliance.
Approved Document S: new buildings and major works in England
If your site is a new non-residential building in England, the building regulations set a minimum. Under Approved Document S (2021 edition, effective 15 June 2022), new non-residential buildings with more than 10 parking spaces must provide at least one chargepoint and cable routes for at least one in five of the remaining spaces.
The same document also sets the specification for those chargepoints: at least Mode 3, a minimum nominal output of 7kW, a universal socket and a dedicated circuit. Approved Document S applies in England. Scotland, Wales and Northern Ireland have their own building standards, so check the rules for your nation before you fix a design.

Cable routes are the cheapest compliance you will ever buy. Ducting laid during construction costs little compared with digging up a finished car park later, which is why we encourage developers and landlords to design for future bays even when they only install a few today.
Layout, accessibility and vehicle compatibility
Standards are not only electrical. Where a charger sits, how a driver reaches it and what they can read on it are design matters too.
Location and accessibility
The Department for Transport’s regulatory review points designers to accessibility guidance reflecting PAS 1899:2022, and asks them to consider fire safety when positioning charging points. PAS 1899:2022 specifies requirements for accessible public chargepoints for all potential users, including disabled and older people. It is written for public chargepoints, but its principles are a sound benchmark for any site where visitors, customers or staff with different needs will charge.
Practical points to build into the layout:
Vehicle charging inlets sit in different places, so cable reach and bay width should work for front, side and rear sockets.
Keep cables from becoming trip hazards across walking routes.
Provide level, unobstructed approaches to the charger, and screens and controls at reachable heights.
Think about fire safety when siting bays next to buildings, escape routes or covered car parks.
Bays, markings and signage
Clear bay markings and signage tell drivers what the space is for and what they need to do. We cover both in our guides to EV charging signage requirements and DfT-aligned bay markings.
Connectors and compatibility
Combined Charging System (CCS) connectors are the main fast-charging standard for cars on UK roads, with Type 2 for AC charging. Your charger specification should state the connector or tethered cable type, and fleet buyers should check it against every vehicle model in the fleet, including vans.
Do the requirements differ by site type?
They do. The electrical core is the same, but the surrounding obligations change with who uses the chargers.
Site type | Typical design priorities | Extra rules to check |
Workplace (staff and visitors) | Long dwell, load management, user authorisation | Smart Charge Points Regulations; Approved Document S for new buildings in England |
Fleet depot | Overnight charging, high total demand, scheduled charging, future growth | Smart Charge Points Regulations; DNO capacity |
Destination (hotels, leisure, retail) | Guest access, payment, signage, sometimes ANPR | Consumer rules if open to the public |
Publicly accessible | Reliability, pricing display, payment, accessibility | Public Charge Point Regulations 2023, PAS 1899 |
For public use, the Public Charge Point Regulations 2023 require maximum prices in p/kWh, roaming, free staffed 24/7 helplines, and contactless payment for new units of 8kW or more and existing units of 50kW or more, subject to exceptions. Those are design inputs because they decide the payment hardware, signal coverage and back-office contracts you need before commissioning. Our summary of public charge point regulations sets out what operators must do, and our guide to payment options for UK businesses compares ways to meet them.
A retail or visitor car park has a further design question, which is how to control who uses the bays. Our piece on retail car park EV charging and ANPR explains why that comes before the first charger. For hotels and leisure sites, see our destination charging articles.
A workplace that opens bays to visitors or the public can move from one column to another. Decide the intended use at the design stage, because adding public access later may mean changing payment hardware, signage and contracts.
Commissioning, testing and maintenance
A design is only compliant once the installation has been tested. The IET Code of Practice includes inspection and testing guidance on earth-electrode resistance, RCD testing and vehicle simulators, and notes that some instruments may not be suitable for RCD-DD testing. Ask your installer which test equipment they use and what certificates you will receive.

The work does not stop at handover. The IET says periodic inspection and testing confirms that installations remain safe for continued use, with the frequency set by environmental influences, usage and the quality of maintenance. A car park charger exposed to weather, vehicle strikes and heavy use is in a harsher environment than most fixed wiring, so build an inspection plan and a fault response process into your operating budget.
Keep a handover pack with the electrical certificates, the maximum demand calculation, the charger commissioning records, the load management settings and the smart charging compliance information. It makes later audits, expansions and ownership changes much simpler.
Grant-funded projects add their own conditions
Public funding often adds specification conditions. OZEV business and fleet grant specifications required installations to follow BS EN 61851, current BS 7671, the IET Code of Practice and ESQCR. The same page, updated on 7 July 2026, states that the grant closed to claims on 26 May 2026. If you are planning now, check the funding position and the conditions of any current scheme, including local authority and regional programmes, before you lock the design. Our grant eligibility checker is a good starting point.
Although that scheme has closed, its specification is a useful benchmark. Designing to the same standards keeps you ready for any future funding.
Our perspective on EV charging design
Most compliance problems we see start before a charger is chosen. A site is designed around the hardware, then the supply, earthing or smart charging requirements arrive late and cost money to fix. We start with the site instead. A feasibility and site assessment records the supply, the parking layout and how drivers will use the bays. From that we design the system around BS 7671, the IET Code of Practice and the rules that apply to your type of site, with load management and software included from the start so you can add bays without a major rebuild. We also treat funding and ownership as design questions. Our fully funded, full ownership, joint investment and charging as a service options are there so the right design is not limited by upfront budget. Where renewable technologies such as solar PV or battery storage make sense, we assess them alongside the chargers so the electrical design takes them into account. The result is an installation that is easier to certify, maintain and expand. Swift Charging
Plan a compliant design with Swift Charging
We design, supply, install and manage commercial EV charging for UK businesses, from site assessment through to commissioning and long-term management. Whether you need workplace charging, a fleet depot or a public charging site, we build the design around the standards above. Our maintenance plans keep the installation compliant after handover.

To see what your site could support, book a commercial EV feasibility review.
FAQ
Does BS 7671 apply to every commercial EV charger?
Yes. Government guidance states that commercial chargepoint installations must comply with the current edition of BS 7671, the IET Code of Practice and ESQCR 2002. Section 722 is the part of BS 7671 written for EV charging, so your electrical designer should work to it from the start.
Do I need an earth rod for outdoor chargers?
Not always. On a PME supply, Section 722 requires one of five listed measures for outdoor or potentially outdoor charging points. An earth electrode is one option, and voltage-operated protection is another. Your designer chooses the method after assessing the site and the charger.
Are the Smart Charge Points Regulations relevant to workplace chargers?
Usually, yes. They apply to relevant non-public, non-rapid car and van chargepoints, and require smart functionality, demand-side response and default off-peak charging hours. Check the exact scope against your equipment and use before ordering.
Does Approved Document S apply to my existing car park?
It is aimed at new buildings and major works in England, and the non-residential requirement applies to new buildings with more than 10 parking spaces. Existing sites outside that scope are not caught by the same duty, but designing to its specification is sensible for any new installation.
What are the main standards for public charge points?
The Public Charge Point Regulations 2023 cover pricing display, roaming, helplines and contactless payment, while PAS 1899:2022 covers accessibility. Electrical design still follows BS 7671 and the IET Code of Practice.
Sources
Commercial chargepoints: minimum technical specification, GOV.UK
Fifth Edition of the IET Code of Practice for EV Charging Equipment Installation
The Electric Vehicles (Smart Charge Points) Regulations 2021
Future of transport regulatory review: zero emission vehicles
Electric vehicle chargepoint and infrastructure specifications, GOV.UK
Recommended