EV Charging Installation Timeline for UK Businesses


A commercial EV charging project typically takes four to twelve weeks from programme start to commissioning when the site has spare grid capacity. The physical install is the short part, often days. The weeks and months come from the network connection, hardware lead times and approvals. If your site needs a larger supply, the same project can run to six months or more. We run the survey, design, network application, installation and commissioning as one project, so these stages overlap instead of queueing one behind another.
TL;DR
Small sites (up to 70kVA, one to three fast chargers or one rapid): 8 to 12 weeks for the connection, according to UK Power Networks.
Medium and large connections (200kVA and above): around 6 months on average, and longer where the network needs reinforcement.
The distribution network operator (DNO) is the usual bottleneck, not the electricians. The DNO owns the local grid and must approve your connection.
Start early: order hardware on the day you sign and run the DNO application alongside it.
Ask us for a feasibility review before you commit to a date, so the timeline rests on your site rather than a guess.
Table of Contents
The timeline at a glance
Treat the project as two clocks. The first is the equipment clock: survey, design, ordering, installation and commissioning. The second is the grid clock: the DNO quote, your acceptance, and any network works. The grid clock usually decides the end date.
Project type | Typical end-to-end timing | What drives it |
Workplace or small site on existing supply | Hardware lead time, DNO notification | |
Small new connection (up to 70kVA) | DNO quote and works | |
Medium or large connection | Network reinforcement, civils | |
Large depot with high-power demand | Can reach 18 to 24 months for a large firm connection | Grid capacity, firm connection |
These are published ranges for the grid side of the project. Your own date depends on your site’s supply, so the survey comes first.
The stages, in order
The IET’s guidance on charging infrastructure sets out the same sequence in a typical deployment: network upgrades and civil works first, electrical equipment installed by qualified people, chargepoints fitted once power is confirmed, then commissioning and notifications. Here is how that looks for a business.

1. Feasibility and site survey
This establishes how much power the site has, where chargers can go and where cables will run. The IET describes surveys at two stages: one for ease of installation, one for the detailed design. It is also where you learn whether a network upgrade is likely, which is the single biggest timeline factor. Our feasibility study covers what is looked at, and you can request a commercial EV feasibility review to start it.
The mistake here is guessing. A site that assumes it has spare capacity and finds otherwise at the quote stage loses months.
2. Design and load management
Design sets the number of chargers, their power, and whether load management (software that shares available power between chargers) lets you fit more bays on the supply you already have. Done well, this can avoid a larger connection altogether. Our guide to fitting more chargers without grid reinforcement explains the approach. For fleets, a depot-first design also keeps upgrade costs down, as set out in our piece on van fleet charging.
3. Network application with the DNO
What you must do depends on the size of the installation:
Notify only. If your maximum demand stays within your agreed supply capacity and EV demand is under 30% of total site demand, you may simply notify the DNO, which an installer can do on your behalf within 30 days after installation.
Apply first. Larger loads need a formal application. Once it is complete, the DNO has a maximum of 65 working days to respond under an Ofgem-enforced standard, and you then have 90 days to accept the offer or lose your place in the queue.
The MCS connections form also sets out that eligible installations are notified within 28 days, and that the DNO should confirm within 10 working days whether the equipment can be connected.
Indicative DNO timescales from the Electric Vehicle Infrastructure Guide:
DNO step | Indicative time |
Quote request | 2 to 13 weeks |
Order acceptance | 4 to 14 weeks |
Civil works | 0.5 to 3 weeks |
Low-voltage DNO works | 6 to 9 weeks |
High-voltage DNO works | 6 to 30 weeks |
Our article on the DNO application process goes into the 15 to 65 working day range in more detail. Handling the paperwork inside the project matters: doing it yourself is described as a 2 to 8 week process that can stall an install, so confirm in writing who owns it. With us, the application sits within the same project as the install.
4. Ordering hardware
Charger lead times run to several weeks. The practical advice is to order on the day the contract is signed so deliveries arrive while the network application is still in progress. When chargers arrive, check them against the purchase order and record serial numbers, which you need for commissioning and warranty. More on this in our guide to EV charging lead times.
5. Installation and civils
Civil works such as trenching, ducting and bay marking are typically the quickest step, half a week to three weeks on the DNO table above. Mounting and wiring chargers on a prepared site is usually measured in days. Surface type, cable run length and car park working hours all change this, which is why the survey records them.
6. Commissioning and handover
Commissioning tests the chargers electrically and confirms they communicate with the management software. The IET guidance notes it is done from both electrical and software perspectives, followed by notifications to the DNO, grant funders and public charging databases. This is also when payment, RFID access and tariffs are switched on if you are charging drivers.
What most often delays a project
Grid capacity. The biggest delay by far. The CMA’s market study recorded one operator’s estimate of around 40 weeks end to end for an ultra-fast site, with around 10 weeks spent waiting for a DNO quote. National Highways guidance says small connections under 1MW can mean a wait of around six months, with larger ones taking 18 months or several years where reinforcement is needed. Those are high-power sites, and a typical workplace is far smaller, but it shows why capacity should be checked first.
Late applications. A DNO offer lapses if you do not accept within 90 days. Decide who signs, and how quickly, before the offer arrives.
Hardware ordered late. Chargers ordered after the grid offer arrives add their full lead time to the end date.
Scope changes. Adding bays after design can trigger a fresh capacity check. Settle the number of chargers, and your growth plan, at the survey.
Meter work. The Electric Vehicle Infrastructure Guide flags meter installation as a bottleneck that early DNO engagement helps plan around.

Realistic examples
A 10-bay office car park on a healthy supply. Survey and design take the first few weeks. With load management, the existing supply may cope, so the DNO step is a notification. Hardware ordered at signing arrives during design. This sits at the quick end of the four to twelve week range.
A hotel adding destination charging with a new small connection. One to three fast chargers or a single rapid charger fall into the small-connection band, so plan on 8 to 12 weeks for the connection, with installation fitted inside that window.
A depot electrifying 50 vans. This is a large-load project. One grid-planning article suggests a 3 to 7 month connection for a 50-vehicle fleet that can charge flexibly. Phasing the fleet and the chargers together keeps vehicles working while capacity arrives. See our fleet electrification timeline and depot charging approach.
How to keep your project on schedule
Survey before you set a date. Commit to dates only after you know your supply position.
Run the clocks in parallel. Start the DNO application as early as the design allows, and order chargers at signing.
Use load management. Sharing power across bays often avoids reinforcement.
Check grant timing. If you plan to use OZEV funding, confirm eligibility before ordering. Our grants eligibility page is the place to start.
Plan phases. Install the first group of chargers now and leave ducting for later expansion.
Agree ownership of paperwork in writing: DNO, grants, commissioning.
Cost moves with the same factors. Our guide to EV charger installation costs shows how connection size feeds into budget.
How we manage the timeline
We design, supply, install and manage commercial charging, from feasibility through commissioning and long-term management, so one team holds the programme. That covers workplace charging, fleet and depot charging and public charging sites. Where eligible, we also help you apply for OZEV grants, and we offer flexible funding models including zero-upfront options. After handover, our maintenance plans and charging software keep the site running.
If you are planning a site, talk to us about a feasibility review.

Our view: the timeline is won before the survey
Most delays we would expect on a commercial project are decided early, when a site commits to a date before it knows its power position. Our approach is to start with the supply, then design around it. We build the programme so the grid application, hardware order and design run side by side. Load management and phased installs are how we aim to get your first chargers live while larger capacity is still being arranged. A single team across survey, DNO paperwork, installation, commissioning and management means fewer handovers and one owner for the schedule. Swift Charging
FAQ
How long does the physical installation take?
On a prepared site, mounting and wiring chargers usually takes days, and civil works such as trenching are typically half a week to three weeks. The longer part of the project is the survey, design, grid approval and hardware delivery around it.
Do I always need DNO approval?
Not always. If the chargers stay within your agreed supply capacity and EV demand is below 30% of site demand, you may only need to notify the DNO. Larger or multi-charger sites usually need a formal application. The survey establishes which applies.
Can I speed up the project?
Yes, mainly by overlapping stages. Order hardware at contract signing, submit the network application early and settle the number of chargers before design is final. Load management can also remove the need for a larger connection.
Why would a project take over a year?
Usually because the site needs a major connection. Industry reporting has described waits of several years where local grid capacity is short, mostly for high-power sites. A feasibility study shows early whether yours is one.