EV Charging Risk Assessment: A Practical Guide for UK Sites


An EV charging risk assessment is a written check of what could go wrong when you add chargers to your site, who could be harmed, and what you will do about it. In practice it has two parts: a fire risk assessment that covers the new chargers and the area around them, and a wider health and safety assessment that covers electrical work, vehicle movement, cables, weather and maintenance. Do it before installation, record it, and review it whenever the site changes.
This guide is for facilities managers, landlords, managing agents and fleet operators. It sets out the hazards to consider, the controls the official and professional guidance points to, and how to keep the paperwork useful.
TL;DR
Carry out the assessment before chargers go in. Government guidance for covered car parks says a fire risk assessment should be done before installing chargepoints, by a competent person.
Cover electrical shock, fire, vehicle impact, trip hazards, weather, theft and maintenance, not just the charger itself.
Record the findings. Since 1 October 2023 all fire risk assessments in England and Wales must be written down, whatever the size of your business.
Review the assessment after installation and after any significant change, such as extra chargers or a new charging area.
Tell your insurer early and keep installation, testing and training records together.
Table of Contents
Why the assessment matters before the first charger goes in
Chargers change a site. They add a high-power electrical supply, vehicles that stay parked for hours while connected, and cables across places where people walk. A fire risk assessment written before installation may no longer describe the building you now run.
The Department for Transport’s interim guidance on covered car parks states that a fire risk assessment should be carried out before chargepoints are installed. Its purpose is to assess the effect on existing fire safety measures and to identify new or increased hazards. It also says to appoint a competent person with sufficient experience of fire safety in car parks.
That guidance is written for covered car parks, but the logic applies to any commercial site: open car parks, depots, hotel forecourts, school grounds and business parks. The question is always the same. What does adding charging do to the risks we already manage?
The legal and technical framework
There is no single “EV charging risk assessment” statute. Several duties overlap, and your assessment should show you have considered each.
Electrical installation. The government’s commercial chargepoint specification requires final installations to follow BS 7671, the IET Code of Practice for Electric Vehicle Charging Equipment Installation, the Electricity Safety, Quality and Continuity Regulations 2002 and other applicable standards. Charging equipment must be installed in line with BS EN 61851. Workplace installations must also comply with the Electricity at Work Regulations 1989.
Fire safety. In England and Wales, the Regulatory Reform (Fire Safety) Order 2005 requires the responsible person to make a suitable and sufficient fire risk assessment. The Fire Protection Association confirms that since 1 October 2023 every fire risk assessment must be recorded, regardless of employee numbers. Scotland and Northern Ireland have their own fire safety legislation, so check the rules that apply to your site.
Competence and training. RoSPA advises that installations should be undertaken by a competent organisation following IET best practice and BS EN 61851-1. It also says employees who are required to charge vehicles should receive information, instruction and training, including what to do if something malfunctions.
Our own view on design is covered in more detail in our guide to EV charging design standards for UK commercial sites.
A five-step method you can follow
The familiar HSE approach works well for chargers. Use it as your skeleton.
Identify the hazards. Walk the proposed charging area and the cable route back to the supply. Note what is nearby: buildings, storage, exits, drainage, traffic routes.
Decide who might be harmed and how. Employees, drivers, visitors, contractors, delivery crews, pedestrians, and anyone with reduced mobility who needs step-free access.
Evaluate the risks and decide on precautions. Rate each hazard, then choose controls. A useful order is the ERIC hierarchy used in the DfT guidance: eliminate, reduce, isolate, control.
Record the findings and put them into action. Name an owner and a date for every control.
Review and update. Set a regular review and define the triggers that bring it forward.
Keep the output short enough that people actually use it: a one-page hazard table, a site plan marked with chargers, isolation points and extinguishers, and a list of linked documents.
Hazards to include
A fleet charging template from a UK health and safety provider lists eight hazards, scored for initial risk out of 25: electric shock (20), vehicle collision near chargers (16), arc flash during maintenance (15), fire or thermal runaway in charger units (15), slips and trips on cables (12), weather-related electrical hazards (12), vehicle battery fire during charging (10) and manual handling of heavy units (9). Treat the scores as an example of how to rank hazards, not as figures for your site. Your own ratings should reflect your layout, your chargers and your users.
Hazard | Who is affected | Typical controls to consider |
Electric shock | Drivers, staff, maintenance engineers | Competent installer, tested and certified circuits, undamaged connectors, regular inspection |
Fire in charger or vehicle | Everyone on site, neighbours | Siting distances, detection, firefighting equipment, manual isolation, staff actions |
Vehicle impact | Drivers, pedestrians | Kerbs, bollards or barriers, marked bays, clear traffic routes |
Trailing cables | Pedestrians, staff | Tidy cable management, bay layout, keeping cables clear of escape routes |
Weather and water | Drivers, engineers | Equipment rated for the environment, drainage, inspection after severe weather |
Theft and vandalism | Site owner, users | Placement, lighting, CCTV, secure equipment |
Maintenance work | Engineers, contractors | Safe isolation, permit or method statement, competent servicing |
Fire controls that matter most
Fire is the hazard property managers and insurers focus on, so give it proper space in the assessment.
Where you put the chargers
As a guide, the Energy Saving Trust says charge points should ideally be at least 10 metres from combustible walls, 7.5 metres from unprotected openings and 10 metres from combustible storage. Indoor charging should be close to exits and preferably at ground level. Underground parking should have at least 120 minutes of fire resistance and adequate ventilation.

On a real site those distances are sometimes impossible to achieve. That is exactly what the assessment is for: record the shortfall, the extra controls you have put in place and who agreed them. Speak to your insurer and a fire safety professional rather than leaving a gap unexplained.
Enclosed and internal charging areas
The fire and rescue service recommendations in RC59 say internal charging areas are hard for firefighters because toxic gases hinder firefighting. Enclosed areas should have at least 60 minutes’ fire resistance, rising to 120 minutes in combustible buildings or basements. The same document recommends suitably designed automatic fire detection and strongly recommends sprinklers for enclosed car parks.
Unattended premises
If chargers run overnight in an unattended building or depot, insurer guidance says to use automatic fire detection maintained to the current BS 5839, provide portable firefighting equipment and safe manual isolation, and to follow the IET wiring regulations and the IET EV installation code. The same guidance says rapid DC chargers should be clearly differentiated from conventional units with explicit signage. Our article on EV charging signage explains what to display and where.
Emergency isolation
Write down where power can be shut off in an emergency, who is allowed to do it, and how a fire crew will find the point. Make sure it is clearly signed and reachable without crossing the hazard.
Protecting people and equipment around the chargers
Most incidents on a site are ordinary ones: a reversing van, a cable across a walkway, a damaged connector. Fire and rescue guidance suggests protecting charge points against mechanical damage with kerbs, bollards or metal barriers. It also recommends clearly marked bays, enough space for inclusive access, cables kept tidy and away from escape routes, plus CCTV and good lighting.
For depots, cable handling deserves its own line in the assessment. Our guide to cable management for fleet and depot operators covers layouts that keep cables off the ground and drivers out of vehicle paths.
Theft and tampering sit within the same assessment. Allianz’s guidance advises considering charge point location and storing charging equipment securely to reduce theft risk. For network-connected chargers, cyber security belongs here too, and we cover both in securing commercial EV chargers against theft and cyberattack.

Installation, commissioning and maintenance
The assessment should not stop once the contractor leaves. Add three things.
Installation records. Chargers should be installed, used and maintained according to the manufacturer’s instructions. Ask your installer for commissioning and test results, including EV-specific checks, and an Electrical Installation Certificate for any new circuit. File them with the assessment.
Servicing. Fire and rescue guidance says servicing should be done by a competent electrician. Set an inspection frequency, record faults and define when a unit must be taken out of use. A written maintenance plan makes this routine rather than reactive.
Training and emergency actions. Staff who charge vehicles or manage the site should know how to use the equipment, how to isolate it safely and what to do in a fire or malfunction. Write the actions down and display them near the chargers.
Insurance: tell them early
The Energy Saving Trust advises businesses to carry out a fire and safety risk assessment before developing EV infrastructure, train staff and drivers on safe charging, make sure charge points meet insurer requirements and guidance, and keep insurers informed about planned charging infrastructure and fleet expansion. Treat your insurer as a stakeholder in the assessment. Our guide to EV charging insurance for UK businesses lists the cover, warranties and checks to raise.
When to review the assessment
Under Article 9 of the Fire Safety Order, the responsible person must review the assessment regularly and particularly if it may no longer be valid or there has been a significant change. That includes significant changes, extensions or conversions to the premises, and changes to technical or organisational measures or how work is organised.
Adding chargers is such a change. A common gap is that chargers are bought as an amenity project with electrical sign-off but no fire safety review, so the fire risk assessment keeps its pre-installation date. Check the date on yours.
Good triggers for an early review:
adding chargers or moving from AC to DC rapid charging
changing the charging area, layout or parking arrangement
a near miss, fault or incident
a change in fleet vehicle types or charging schedules
new tenants, building works or changes to nearby storage
updated official guidance or a request from your insurer
Perspective: build the assessment into the project
We see the best results when the risk assessment is part of the project from the first site visit, not a form completed at handover. Our approach is to start with a feasibility review and site assessment, then design the installation around what that review finds: supply capacity, charger positions, cable routes, load management and how drivers will use the site. When layout and safety are decided together, controls such as bollards, signage, lighting and isolation points cost far less to include than to retrofit. We also think management matters as much as hardware. Smart charger software and load management give you visibility of faults and usage, and an ongoing maintenance agreement keeps inspection and servicing on a schedule you can show in your records. The aim is straightforward: chargers that are safe, reliable and commercially viable, with a paper trail your insurer and fire safety adviser can follow. Swift Charging
Where Swift Charging can help
If you are planning chargers for a workplace, depot or visitor site, we can support you from feasibility and design through installation, commissioning and long-term management. We provide AC and DC solutions, workplace charging, fleet and depot charging, charging software and maintenance, and we help eligible businesses apply for available government grants.

A good first step is our Commercial EV Feasibility Review. It looks at your site, your supply and your charging needs so risks can be designed out early. For a view of what the study covers, read our guide to the EV charging feasibility study. You can also check your OZEV grant eligibility to see whether funding could reduce installation costs.
A short checklist to take to site
Use this as a prompt list when you walk the site with your installer or adviser.
Has a competent person assessed the impact of chargers on existing fire safety measures?
Are charger positions clear of combustible walls, openings and storage, or is any shortfall recorded with extra controls?
Is there automatic fire detection, portable firefighting equipment and a signed manual isolation point?
Are chargers protected from vehicle impact, and are bays and walkways clearly marked?
Are cables managed so they do not cross escape routes or pedestrian paths?
Are DC rapid chargers distinguished with signs?
Do you hold test certificates, commissioning records and the manufacturer’s instructions?
Has your insurer been told, and are staff trained?
Is the assessment recorded, dated, owned and scheduled for review?
FAQ
Is an EV charging risk assessment a legal requirement?
There is no standalone requirement with that name, but the duties behind it are legal. In England and Wales the responsible person must keep a recorded fire risk assessment, and workplace installations must comply with the Electricity at Work Regulations 1989. Government guidance also expects a fire risk assessment before installing chargepoints in covered car parks.
Who should carry out the assessment?
Use a competent person. For fire risk in car parks, government guidance says to appoint someone with sufficient fire safety experience in that setting. The electrical installation itself should be done by a competent organisation following the IET code and BS 7671.
Do I need to update my fire risk assessment after installing chargers?
Yes, in most cases. Installing charging infrastructure is a significant change to the premises, so Article 9 expects a review. If your assessment still carries its pre-installation date, bring it forward.
What should I do about charging near a building or underground car park?
Record the distances and the building construction, then speak to your insurer and a fire safety professional. The guidance points to fire resistance of 60 to 120 minutes for enclosed areas, detection, sprinklers for enclosed car parks, ventilation and charging positions close to exits.
Sources
Covered car parks: fire safety guidance for electric vehicles (Department for Transport)
Commercial chargepoints: minimum technical specification (GOV.UK)
Is a fire risk assessment a legal requirement? (Fire Protection Association)
Free EV fleet charging risk assessment template (Health Safety Zone)
Insuring depot charging infrastructure (Energy Saving Trust)
RC59: Recommendations for fire safety when charging electric vehicles
Guidance on the premises and charging of electric vehicles (Allianz)
Recommended