EV Charging Lead Times for UK Businesses: What to Expect

Writer: Swift Charging
Swift Charging
Nov 14
10 min read

Transformer and trench at a UK fleet depot

For a UK business, the time from first survey to a working charger runs from a few weeks to well over a year. The grid connection sets that time, not the charger. A small site using its existing supply can be live in a few months. A site that needs a bigger connection or network reinforcement can wait 6 to 18 months or longer. We manage the whole process for commercial sites, so the sections below set out each stage, the published timescales, and what shortens the wait.



TL;DR

 

  • Small sites: the Distribution Network Operator (DNO, the company that owns the local electricity network) issues a connection quote in 5 to 65 working days, depending on connection size.

  • Larger sites: where network upgrades are needed, industry guidance points to 6 months or more, and to years for very large connections.

  • On site: civils, electrical work and commissioning typically take 5 to 10 weeks once the power is secured.

  • Biggest saving: apply to the DNO in the same week as your site survey, and design the site so it needs less power at first.

 

Table of Contents

 

 

Where the time goes in a commercial EV charging project

 

Most businesses assume the wait is for chargers to be delivered and fitted. In practice that is the shortest part. The long part is the electricity supply: whether your site has enough spare capacity, and if not, how long the network operator takes to provide it.

 

A typical commercial project runs through six stages. These are the stage durations in our own installation cost guide:

 

Stage

What happens

Typical duration

1. Scoping

Define the number of sockets, power needs and site constraints

1 to 2 weeks

2. Site survey

Assess existing supply, layout and civils requirements

1 to 2 weeks

3. DNO estimate and quote

Network operator assesses capacity and quotes

5 to 65 working days

4. Detailed design

Final layout, cable routes, load management

2 to 4 weeks

5. Civils and electrical works

Trenching, cabling, charger installation

4 to 8 weeks

6. Commissioning and handover

Testing, certification, staff training

1 to 2 weeks

Added end to end, those stages come to roughly 10 weeks at the fastest and around 31 weeks at the slowest, before any network reinforcement. Stages overlap when they are managed well, which is why the order and timing of your applications matter more than any single stage.

 

The table covers the case where the existing supply, or a modest new connection, is enough. If your site needs substantial new capacity, stage 3 changes completely, and that is where the long lead times come from.


Where the time goes in a commercial EV charging project

How long DNO applications and grid connections take

 

The DNO is the single biggest variable. Every site connects to one of the regional network operators, and you have no choice of operator: it is set by where your site is.

 

The official timescales

 

GOV.UK states that the DNO issues a connection quote within 5 to 65 working days, depending on the size of the connection. The same guidance says smaller connections that use an existing street cable can take a few weeks to deliver, while very large connections may take many months or sometimes years. Once you have a quote, you have 90 days to accept or reject it.

 

The quote is not the end of the wait. After you accept and pay, the DNO agrees a programme with you and gives a date for its work, as the Energy Networks Association’s fleet guidance describes.

 

Indicative connection times by size

 

Different bodies publish different figures, so treat them as ranges rather than promises:

 

  • SSEN’s EV guide gives 4 to 8 weeks for small connections (up to 70 kVA), 8 to 16 weeks for medium (69 to 200 kVA) and 3 months or more for large connections (over 200 kVA). Those figures date from 2018, so check your own DNO’s current published times.

  • The Battery Electric Truck Trial guidance gives 8 to 12 weeks for small (up to 70 kVA) and medium (200 kVA to 1,000 kVA) connections, and 6 months or more for large connections above 1,000 kVA.

  • National Highways’ truckstop guidance (May 2026) says upgrading a grid connection under 1 MW may take around 6 months, while larger connections can take 18 months or, where significant reinforcement is needed, several years.

  • BEAMA’s guide to EV infrastructure reports a typical timescale of about 9 to 10 months from initial application to energisation of EV chargers.

 

The pattern is consistent. Under about 70 kVA you are usually looking at weeks to a few months. Between 70 kVA and 1 MW you plan for several months. Above that, you plan for a year or more and start immediately.

 

Why the figures differ so much

 

These sources are measuring different things: a quote versus a completed connection, a single charger versus a depot, a quiet network versus a constrained one. The SSEN guide also notes that the time depends on the number and type of chargers, from a few fast chargers on a single-phase supply up to a rapid charger on a three-phase supply. Whatever the source, your own DNO’s quote is the only figure that applies to your site.

 

What makes lead times longer

 

Four factors account for most of the delay on commercial projects.

 

1. Connection size. The more power you ask for, the more likely the local network needs work. GOV.UK ties delivery time to connection size and the complexity of the work.

 

2. Network reinforcement. When the local cable, transformer or substation cannot carry the extra load, the DNO must upgrade it first. National Highways attributes long waits to the connection queue and notes that times vary by DNO and by the engineering involved.

 

3. Poor design planning. BEAMA says electrical infrastructure is unique to each site and that weak design planning can delay civils work, increase costs and lead to contractual disputes. A survey that misses a buried service or an awkward cable route costs weeks later.

 

4. Starting in the wrong order. Many businesses choose chargers, then survey, then apply to the DNO. Because the DNO stage cannot be compressed once started, applying last adds its whole duration to the end of your project.

 

A change that helps: reinforcement charges

 

From 1 April 2023, demand connection customers such as EV chargepoint operators are no longer charged for distribution network reinforcement needed to accommodate the connection. That changes the cost of upgrades, not the time they take: reinforcement still has to be designed and built.

 

Possible queue reform

 

In February 2025 Ofgem proposed a system that prioritises projects that are ready and needed, replacing first-come, first-served, with first connections operational from 2026. Being ready, with a surveyed site, a clear need and a decided design, is the practical way to benefit from any queue that rewards readiness.

 

The stages in order, and how to avoid delays

 

GOV.UK advises early discussion with the network operator when you are installing multiple chargepoints. For a very small installation, an installer can tell you whether the DNO must be involved before or after the works. Here is the sequence we follow for commercial sites, with where each stage goes wrong.

 

1. Scope the project around real demand

 

Decide how many vehicles need charging, when they are on site and how far they travel. Over-specifying power is the quickest way to trigger a larger connection. Our guide to EV charging power requirements explains how to size a site without paying for capacity you will not use. The usual mistake is to size for the day the whole fleet is electric rather than for the first phase.

 

2. Survey the site and apply to the DNO together

 

The survey tells you the existing supply capacity, where cabling can run and what civils work is needed. Request the DNO budget estimate in the same week. Our own advice is that it is the one task you cannot compress once it starts, so starting late anywhere else costs far less than starting late here.


Surveyor inspecting commercial electrical supply and cable routes

3. Use the quote period to design

 

While the DNO assesses capacity, finalise the layout, cable routes and load management. Design typically takes 2 to 4 weeks, so it fits inside a longer DNO window without extending the project. If you have a 90-day decision window, use it to confirm funding, including any grant, before you accept.

 

4. Reduce the power you need to ask for

 

National Highways says operators can sometimes cut grid-connection delivery time by reducing technical complexity or using smart connection solutions. It also says an incremental approach works in grid-constrained locations: install the first chargepoints while upgrades are delivered for later phases.

 

In practice that means three levers:

 

  • Load management, which shares available power between chargers so a smaller connection supports more bays. See our playbook on fitting more chargers without grid reinforcement.

  • Phasing, which installs what the current supply allows now and adds more as capacity arrives. Our guide to deferring DNO upgrades covers how to do this without stranding the later phases.

  • Smart or ramped connections, agreed with the DNO, which let you energise at a lower level while reinforcement is completed.

 

5. Build and commission

 

Civils and electrical works typically take 4 to 8 weeks on site, followed by 1 to 2 weeks of testing, certification and staff training. Delays here are almost always inherited from earlier stages: a late quote, a design change or an unplanned service on the route.

 

Realistic timelines by type of site

 

These are planning ranges built from the published figures above, not guarantees. Your DNO’s quote overrides them.

 

Site type

Likely connection need

Planning horizon

Small workplace or hotel car park, a handful of chargers

Existing supply or a small connection (up to 70 kVA)

Weeks to a few months from survey to live

Larger workplace, business park or school

Medium connection (up to about 200 kVA)

Roughly 3 to 6 months, often longer with design and works

Fleet depot with many vehicles

Large connection (200 kVA to 1 MW)

6 months or more, sometimes nearer a year

Large depot or multi-bay public hub

Above 1 MW, possible reinforcement

18 months or more, in some cases years

For depots, the operational pattern also matters. If vehicles park overnight for long periods, you need far less power per vehicle than a design that assumes fast turnaround. Our fleet depot charging guide sets out that operational-first approach.

 

Lead times and the other things that move with them

 

Cost

 

Grid connection and transformer or substation work are among the items that surprise buyers most, and they are the same items that stretch the schedule. For budgeting alongside timelines, see our commercial EV charger installation cost guide.

 

Grants

 

If you plan to apply for OZEV funding, the grant application belongs in stage 2, alongside the survey, because eligibility and requirements shape the design. You can check your eligibility before you commit to a layout.

 

Retail and public sites

 

Public-facing sites have extra items, such as payment and access control, that should be settled during design rather than after the build. Our guide to retail car park EV charging covers the sequencing.

 

What we do about lead times

 

We run the site survey, DNO liaison, grant applications and commissioning as one coordinated project, so the stages overlap rather than queue. For a reader who has never dealt with a network operator, that matters. You do not have to learn the DNO’s application route, chase quotes or reconcile design with what the network will actually supply.

 

  The most common mistake we see is treating the DNO application as a step after choosing chargers. It should be the first thing in motion, because it is the one stage nobody can speed up once it has begun.   Our approach is to start the DNO estimate alongside the site survey, then design the site to need as little new capacity as the operation allows. Smart load management, phased installation and renewable options such as solar PV and battery storage can all reduce the size of the connection you ask for, and a smaller request is usually a quicker one.   We also think about the life of the site, not only the first day. Chargers that are managed on one platform, with maintenance and support in place, keep earning their place on the grid connection you waited for.   Swift Charging

Our view on lead times

 

Plan your connection with Swift Charging

 

If your site needs a DNO application, a grant check or a phased design, we handle the process from feasibility to commissioning and long-term management. Our workplace charging and fleet charging services both start with a site assessment, and you can request a commercial EV feasibility review to find out where your site stands on capacity and timescale.


Swiftcharging

For funded options, we also offer zero-upfront and funded models, so the wait for a connection need not be a wait for budget as well. Our main commercial EV charging page shows the options.

 

FAQ

 

How long does a DNO application take for EV charging?

 

The DNO issues a connection quote in 5 to 65 working days, depending on the size of the connection, according to GOV.UK. You then have 90 days to accept it. After acceptance and payment, the DNO agrees a programme and a date for its own works, which can add weeks or many months.

 

How long does it take to install commercial EV chargers once the power is available?

 

On our projects, civils and electrical works typically take 4 to 8 weeks on site, followed by 1 to 2 weeks of commissioning, testing and staff training. Smaller sites with fewer chargers sit at the shorter end.

 

Why do some sites wait more than a year?

 

The cause is usually network reinforcement. When the local network cannot carry the extra load, the DNO has to upgrade it first, and guidance for larger connections points to 18 months or, in some cases, several years. The sooner the application goes in, the sooner you are in the queue.

 

Can I shorten the wait?

 

Yes, in three ways: apply to the DNO at the same time as the survey, reduce the power you request using load management, and install in phases. National Highways’ guidance says smart connection solutions and incremental deployment can reduce the impact of grid constraints.

 

Do I still pay for network reinforcement?

 

No, not for a demand connection such as an EV chargepoint. Since 1 April 2023, these customers are not charged for distribution network reinforcement needed to accommodate the connection. Other connection costs may still apply.

 